PROJECT SCHEDULE
Phase 1 : Project Programming (January 20 - March 6, 2026)
Stakeholder Engagement: February 18-20
Community Input Survey: February 18 - March 3
Input Review & Program Finalizing: March 3-6
Phase 2 : Preliminary Concept Master Plan Design Phase (March 9 - April 21, 2026)
Prepare 2 Concept Design Options
Resident Presentation: April 15 - 6pm at Betty Russell Park
Board Presentation: April 21 - 7pm at Viking Park
Phase 3: Final Draft Master Plan Design Phase (April 22 - May 19, 2026)
Revise 1 Concept Design
Resident Presentation: May 13, 2026 - 6pm at Betty Russell Park
Board Presentation: May 19, 2025 - 7pm at Viking Park
Phase 4 : Final Master Plan Design Phase (May 20 - July 1, 2026)
Finalize Concept Design and Supporting Materials
Resident Presentation: June 10, 2026 - 6pm at Betty Russell Park
Board Presentation: June 16, 2025 - 7pm at Viking Park