UPCOMING MEETINGS

Community Input Survey

February 18th - March 3rd

An interactive session for residents to provide ideas.


PROJECT SCHEDULE

Phase 1 : Project Programming (January 20 - March 6, 2026)

Stakeholder Engagement: February 18-20 

Community Input Survey: February 18 - March 3

Input Review & Program Finalizing: March 3-6

Phase 2 : Preliminary Concept Master Plan Design Phase (March 9 - April 21, 2026)

Prepare 2 Concept Design Options 

Resident Presentation: April 15 - 6pm at Betty Russell Park

Board Presentation: April 21 - 7pm at Viking Park

Phase 3: Final Draft Master Plan Design Phase (April 22 - May 19, 2026)

Revise 1 Concept Design 

Resident Presentation: May 13, 2026 - 6pm at Betty Russell Park

Board Presentation: May 19, 2025 - 7pm at Viking Park

Phase 4 : Final Master Plan Design Phase (May 20 - July 1, 2026)

Finalize Concept Design and Supporting Materials

Resident Presentation: June 10, 2026 - 6pm at Betty Russell Park

Board Presentation: June 16, 2025 - 7pm at Viking Park

Phase 5 : OSLAD Application to IDNR (July 1 - September 30, 2027)

Phase 6 : Phase 1 Construction Documentation & Permitting (April - October 2028)

Phase 7 : Phase 1 Construction (Summer 2029)